April 2, 2025
BY Tidewater Renewables Ltd.
Tidewater Renewables Ltd. reports that, at approximately 9:00 a.m. (MST) on April 1, 2025, there was a minor fire (the "Incident") in the main renewable diesel process unit at the corporation's renewable diesel refinery (the "HDRD complex") located in Prince George, British Columbia.
The Incident has been extinguished and the impacted area of the HDRD complex has been isolated and stabilized. The corporation confirms that all personnel are accounted for and no injuries have been reported at this time.
The corporation continues to investigate the Incident, both on its own behalf and in cooperation with the applicable regulatory authorities. While the investigation is in its early stages, Tidewater Renewables is encouraged by the seemingly low level of damage resulting from the Incident.
Advertisement
The corporation maintains a full suite of spare parts at the HDRD complex and should be in a position to rectify the damage and complete the appropriate testing and analysis required to safely bring the HDRD complex back online in short order. Given the product inventory levels maintained at the HDRD complex, the outage is not expected to have a material impact on Tidewater Renewables' operating and financial results (assuming the resumption of operations as expected). Tidewater Renewables will provide more information as the investigation into the Incident progresses if any new information comes to light.
Advertisement
Tidewater Renewables Ltd. has reported that its biorefinery in Prince George, British Columbia, operated at 88% capacity last year. A final investment decision on the company’s proposed SAF project is expected by year end.
BDI-BioEnergy International has signed a contract with Ghent Renewables BV to begin the construction of a pioneering biofuel feedstock refinery plant. Construction is underway and the facility is expected to be operational by the end of 2025.
Verity Holdings LLC, a subsidiary of Gevo Inc., has partnered with Minnesota Soybean Processors (MnSP) to implement Verity’s proprietary track and trace software. The collaboration aims to unlock additional value through export premiums.
IAG and Microsoft are extending their 2023 co-funded purchase agreement for SAF by five years. The SAF used under the agreement will be produced by Phillips 66’s Humberside refinery and LanzaJet’s facility in the U.S.
U.S. exports of biodiesel and biodiesel blends of B30 or greater fell to 7,849.6 metric tons in February, according to data released by the USDA Foreign Agricultural Service on April 3. Biodiesel imports were at 21,964.9 metric tons for the month.